Our Big Cat Project is moving swiftly toward its next milestone. Here’s a snapshot of where things stand and what’s coming soon.


Current Progress

  • Earthwork — 99% Complete
    Final grading and compaction are nearly finished, providing a stable platform for roads, utilities, and vertical construction.

  • Utility Installation — ≈ 50% Complete
    Three dedicated crews are installing water, sewer, and storm-drain systems in parallel. Main trunk lines are in, and lateral connections are progressing block by block.


What’s Next?

 

Date Milestone Details
May 1 Road Crews Mobilize (Phase 1) Asphalt and base-course specialists arrive on site to begin sub-grade prep.
Mid–Late June First Lift of Pavement Target window to pave the entire site’s primary roadway network.
Summer 2025 Vertical Construction Kickoff On-schedule start for building pads once utilities and roads are certified.

Key Goals for the Next 60 Days

  1. Finish the final 1% of earthwork
    • Final compaction tests and survey sign-off.

  2. Push utilities past the 75% mark
    • Maintain three active crews; add night shift if needed to stay ahead of schedule.

  3. Prepare sub-grade for paving
    • Moisture-density checks and proof-rolls ahead of the May 1 road-crew arrival.


Safety & Quality Commitments

  • Daily toolbox talks keep crews aligned on safety protocols.

  • Third-party testing verifies compaction, pipe bedding, and asphalt density.

  • Environmental controls remain active to minimize dust and storm-water runoff.

  • More information: Florida Department of Transportation – Construction

Stay Connected

Follow our progress on social media for photos, drone flyovers, and real-time milestones as Big Cat continues to take shape.

Questions? Contact our project hotline at (555) 123-4567 or email bigcat@yourcompany.com.


Thank You

To our field teams, subcontractors, and community partners—your hard work and support fuel this project’s success. Stay tuned for more updates as we roar ahead!

#BigCatProject #ProjectUpdate

Project Gallery

big cat project advance
tampa bay big cat project advance

Contact us about Your Next Project

Feel Free To Drop Us A Line To Contact Us

    FIRST NAME *

    LAST NAME *

    EMAIL ADDRESS *

    PHONE NUMBER

    SUBJECT

    HOW CAN WE HELP?